Perbandingan Analisa harga satuan Pasangan Bata Ringan VS Pasangan Bata Merah
Berikut ini Analisa Harga Satuan Pasangan Dinding Bata Ringan VS Pasangan Dinding Bata Merah
Untuk versi excel / xls KLIK DISINI
ANALISA HARGA SATUAN | |||||||||
KODE ANALISA | : | D.001 | |||||||
JENIS PEKERJAAN | : | Pasangan bata ringan tebal 7,5 cm dengan mortar semen | |||||||
SATUAN PEMBAYARAN | : | m² | |||||||
PERKIRAAN | HARGA | JUMLAH | |||||||
NO. | KOMPONEN | SATUAN | KUANTITAS | SATUAN | HARGA | ||||
(Rp.) | (Rp.) | ||||||||
A. | TENAGA | ||||||||
1 | Pekerja Biasa | L17 | Org/hr | 0.3000 | 50,000.00 | 15,000.00 | |||
2 | Tukang Batu | L07 | Org/hr | 0.1000 | 60,000.00 | 6,000.00 | |||
3 | Kepala Tukang Batu | L02 | Org/hr | 0.0100 | 65,000.00 | 650.00 | |||
4 | Mandor | L01 | Org/hr | 0.0150 | 70,000.00 | 1,050.00 | |||
JUMLAH HARGA TENAGA | 22,700.00 | ||||||||
B | BAHAN | ||||||||
1 | Bata ringan | M022 | bh | 8.3333 | 6,120.06 | 51,000.51 | |||
2 | Mortar | M037 | zak | 0.08 | 98,000.00 | 7,350.00 | |||
JUMLAH HARGA BAHAN | 58,350.51 | ||||||||
C | PERALATAN | ||||||||
JUMLAH HARGA PERALATAN | - | ||||||||
D | JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C) | 81,050.51 | |||||||
Asumsi Harga per m3 bata ringan | = | 680,000.00 | |||||||
Asumsi Harga mortar per zak | = | 98,000.00 | |||||||
ANALISA HARGA SATUAN | |||||||||
KODE ANALISA | : | D.002 | |||||||
JENIS PEKERJAAN | : | Pasangan bata merah tebal 1/2 bata, 1 Pc : 6 Ps | |||||||
SATUAN PEMBAYARAN | : | m² | |||||||
PERKIRAAN | HARGA | JUMLAH | |||||||
NO. | KOMPONEN | SATUAN | KUANTITAS | SATUAN | HARGA | ||||
(Rp.) | (Rp.) | ||||||||
A. | TENAGA | ||||||||
1 | Pekerja Biasa | L17 | Org/hr | 0.3000 | 50,000.00 | 15,000.00 | |||
2 | Tukang Batu | L07 | Org/hr | 0.1000 | 60,000.00 | 6,000.00 | |||
3 | Kepala Tukang Batu | L02 | Org/hr | 0.0100 | 65,000.00 | 650.00 | |||
4 | Mandor | L01 | Org/hr | 0.0150 | 70,000.00 | 1,050.00 | |||
JUMLAH HARGA TENAGA | 22,700.00 | ||||||||
B | BAHAN | ||||||||
1 | Bata Merah | M022 | bh | 70.0000 | 550.00 | 38,500.00 | |||
2 | Portland Cement (PC) | M037 | kg | 8.3200 | 1,450.00 | 12,064.00 | |||
3 | Pasir Pasang | M002 | m³ | 0.0490 | 181,700.00 | 8,903.30 | |||
JUMLAH HARGA BAHAN | 59,467.30 | ||||||||
C | PERALATAN | ||||||||
JUMLAH HARGA PERALATAN | - | ||||||||
D | JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN (A + B + C) | 82,167.30 | |||||||